Ιαν 18, 2017 | Case Study, Jenbacher Case Study, Natural Gas Case Studies, Romania Case Studies
The 22.8MW full turnkey power plant project at VEST ENERGO was completed in three stages. The generated electricity produced by the engines is injected in National Energy System (SEN), while the heat is delivered to Bucharest’s district-heating system (RADET). Clarke...
Ιαν 18, 2017 | Case Study, Natural Gas Case Studies, Romania Case Studies
BEPCO was the first large scale district heating project in Romania utilising internal combustion engines. BEPCO built, owns and operate four cogeneration power plants for district heating în Brasov; The electricity is injected in SEN (National Power Grid), while the...