22.8MW Full Turnkey Power Plant Delivered to VEST ENERGO, Romania

The 22.8MW full turnkey power plant project at VEST ENERGO was completed in three stages.

The generated electricity produced by the engines is injected in National Energy System (SEN), while the heat is delivered to Bucharest’s district-heating system (RADET).

Clarke Energy delivered a full turnkey for VEST ENERGO, four engines were commissioned for Stage 1 and Stage 2 :

Electrical Output 2 x 3,045 MW / Thermal Power 2 x 3,042 MW

Electrical Output 2 x 4,034 MW / Thermal Power 2 x 3,852 MW

For VEST ENERGO Stage 3 Clarke Energy delivered two engines JMS 624 having:

Electrical Output 2 x 4,401 MW/ Thermal Power 2 x 3,969 MW

The engines fleet was delivered, installed and commissioning by Clarke Energy Romania;

The engines run between 8000 and 8100 hours per year;

Clarke Energy Romania service team provide the preventive and corrective maintenance of CHP engines, through the service contract;

Client: 
VEST Energo
Capacity: 
22.8 MWe
Location:
Bucharest, Romania 
Commissioning:
17.11.2010
24.06.2011
17.07.2014
Maunfacturer:
GE (now INNIO) Jenbacher
Installation By:
Clarke Energy Romania
Type:
2 x JMS 620
2 x JMS 624
2 x JMS 624
Primary Fuel: Natural Gas

 

More Case Studies

High-Efficiency Cogeneration in Botoșani, Romania

High-Efficiency Cogeneration in Botoșani, Romania

Clarke Energy has expanded the high-efficiency cogeneration capacity of the Municipality of Botoșani’s district heating network with a new INNIO Jenbacher JMS 624 gas engine. The installation integrates with two units supplied in 2012, improving efficiency, reducing primary energy consumption, and supporting lower emissions across SACET Botoșani.

Any Further Questions?

If you have any technical questions that need answering, would like to arrange to speak to a sales advisor or book a feasibility study.