Engineering Data-Center Reliability with Prime-Running Gas Engines

by A. Marshall, A. Wray-Summerson and V.Barran.

From 99.9% to 99.999% Availability

Data-center reliability is rarely a binary question of “does it work or not?” Instead, it is defined by explicit availability tiers – typically three nines (99.9%), four nines (99.99%), or five nines (99.999%) – each with very different implications for system architecture, redundancy, and cost.

Modern gas-engine power plants, built from multiple individual prime-running engines, offer a flexible way to design across these tiers using the same core technology. The difference lies not in the engines themselves, but in how many are installed and how they are operated.

Individual Engines vs Plant Availability (A Necessary Distinction)

Before looking at configurations, one clarification is critical:

  • Individual gas engines are typically designed for 8,000–8,300+ operating hours per year in prime or continuous duty.
  • This corresponds to single-unit availability in the ~97.5–98.5% range, including planned maintenance.
  • Data-center availability targets (99.9%–99.999%) apply to the aggregated power plant, not to individual engines.

This mirrors how data centers already think about:

  • UPS modules
  • Battery strings
  • Power distribution paths

No single component is “five nines.” The system is.

Availability Targets in Data-Center Terms

Article content

The jump from 3×9s to 5×9s is not incremental – it is architectural.

Base Case Assumptions (Common to Both Designs)

To keep the comparison clean, both configurations use the same fundamentals:

  • Critical IT load: 50 MW
  • Engine rating: 3.3 MW electrical – (here we take the Jenbacher J620 as an example, but it could also be a 4.5MW Jenbacher J624 block.)
  • Engine duty: Prime operation (8,000–8,300+ hours/year per engine)
  • Fuel: Natural gas / renewable gas capable
  • UPS/BESS: Assumed for ride-through and power quality

Minimum engines required to meet load:

50 / 3.3 = 15.15 -> 16 engines (N)

Configuration 1: 99.9% Availability (3×9s)

High Availability, Cost-Optimised Architecture

Target

  • Maximum downtime: ~8.76 hours per year
  • Typically acceptable where brief, non-catastrophic outages can be tolerated

Recommended Architecture: N+1

  • Engines required for load (N): 16
  • Redundancy: +1
  • Total installed: 17 × 3.3 MW = 56.1 MW

How It Performs

  • One engine can be unavailable (planned or forced) with no loss of load
  • Planned maintenance is sequenced
  • Forced outages are absorbed automatically

At this redundancy level:

  • Multiple simultaneous failures are unlikely but not impossible
  • The system comfortably meets 99.9% availability, but not higher tiers

Where This Fits

  • Enterprise data centers
  • Regional colocation
  • Edge or industrial-adjacent facilities
  • Grid-parallel sites with some tolerance for short interruptions

This is the minimum “data-center-credible” prime-power configuration.

Configuration 2: 99.999% Availability (5×9s)

Hyperscale-Grade, Fault-Tolerant Architecture

Target

  • Maximum downtime: ~5.26 minutes per year
  • Effectively “always on” from an operational perspective

Recommended Architecture: N+4 (or N+3 with Operational Constraints)

A five-nines target assumes:

  • Planned maintenance never causes loss of redundancy
  • At least two unplanned events can occur without service interruption

A conservative design is N+4.

  • Engines required for load (N): 16
  • Redundancy: +4
  • Total installed: 20 × 3.3 MW = 66.0 MW

What This Enables

  • One engine offline for maintenance
  • One engine unavailable due to forced outage
  • One engine unavailable due to auxiliary or balance-of-plant fault
  • Still ≥ 50 MW available

The probability of four simultaneous unavailable engines is extremely low, even with conservative single-unit availability assumptions.

This is how five-nines availability is achieved without five-nines machines.

Why Prime-Running Engines Support Ultra-High Availability

Engines operating 8,000+ hours per year offer several reliability advantages:

  • Reduced thermal cycling
  • Continuous lubrication stability
  • Early detection of latent faults
  • Maintenance becomes predictable and schedulable

Failures are discovered during operation, not during emergency start-up.

For five-nines systems, this matters more than nameplate efficiency.

System Integration Still Matters

At higher availability tiers, engines are part of a stack, not a standalone solution:

  • UPS: Millisecond ride-through and isolation, power quality
  • BESS: Black start, transient response, fast reserve, power quality
  • Grid: Capacity firming, not primary reliability
  • Controls: Automated dispatch, load sharing, fault isolation

The engines provide energy reliability; electronics handle power continuity. UPS and BESS also support power quality.

The Strategic Takeaway

  • 99.9% availability is achievable with modest redundancy and cost-efficient design
  • 99.999% availability requires deliberate over-provisioning and operational discipline
  • Both can be delivered using the same prime-running gas-engine platform

The difference is not technology. It is architecture, redundancy philosophy, and operational intent.

Conclusion

A 50 MW data center can be engineered across multiple reliability tiers using prime-running gas engines:

50 MW Data Center – Summary Comparison (3.3 MW vs 4.5 MW)

Article content
50MW Data Center – Summary Comparison (3.3MW Vs 4.5MW)

Each engine is designed for 8,000–8,300+ hours per year. The power plant, through modular redundancy, delivers the availability.

Reliability is not about avoiding failure. It is about designing so failure does not matter.

Find A News Article

Generic filters

Find by Category

Any Further Questions?

If you have any technical questions that need answering, would like to arrange to speak to a sales advisor or book a feasibility study.